Ten weeks from keys to open doors. We are halfway through week 5, and the shop is still on course to open on Saturday, March 13.
Sent Wednesday, February 3, 2027, by Imogen Reyes at Scribe & Miter Build, to the crew and to Tunde at Handbell.
Opening day
Sat, Mar 13unchanged since week 1
Today
Week 5 of 10drywall, day 3 of 5
Done
9 of 232 under way, 12 to come
Spare days
2both in the last week
Done
Under way
To do
Milestone
Has to finish first
Jan 18 and Feb 15: public holidays, no site work
Each bar sits on the ten weeks from Jan 4 to Mar 13. The blue line is today. No site work on Mon, Jan 18 or Mon, Feb 15, both public holidays.
1Design and permitsJan 4 – Jan 12
Survey and final drawingsDone
Imogen · Mon, Jan 4 – Thu, Jan 7
Building permit issuedDone
City · Wed, Jan 6
Owner signs off layoutDone
Tunde · Fri, Jan 8After survey and final drawings
Order long-lead itemsDone
Imogen · Mon, Jan 11 – Tue, Jan 12After owner signs off layout
2Demolition and rough-inJan 11 – Feb 5
Demolition and clear-outDone
Kofi · Mon, Jan 11 – Thu, Jan 14After building permit issued
Plumbing rough-inDone
Marta · Tue, Jan 19 – Fri, Jan 22After demolition and clear-out
Electrical rough-inDone
Dev · Tue, Jan 19 – Wed, Jan 27After demolition and clear-out
Hood and ventilationDone
Kofi · Mon, Jan 25 – Thu, Jan 28
Rough-in inspectionDone
City · Fri, Jan 29After electrical rough-in + hood and ventilation
Drywall and patchingUnder way
Kofi · Mon, Feb 1 – Fri, Feb 5After rough-in inspection
3Finishes and millworkJan 19 – Mar 2
Counter built off siteUnder way
Aylin · Tue, Jan 19 – Fri, Feb 12After order long-lead items
FlooringTo do
Rhys · Mon, Feb 8 – Thu, Feb 11After drywall and patching
PaintingTo do
Rhys · Fri, Feb 12 – Thu, Feb 18After flooring
Counter installedTo do
Aylin · Fri, Feb 19 – Wed, Feb 24After counter built off site + painting
Lights, outlets and faucetsTo do
Dev, Marta · Thu, Feb 25 – Tue, Mar 2After counter installed
4Equipment and openingMar 1 – Mar 13
Espresso machine deliveredTo do
Supplier · Mon, Mar 1
Sign and storefrontTo do
Kofi · Mon, Mar 1 – Wed, Mar 3
Equipment hooked up, testedTo do
Marta · Wed, Mar 3 – Thu, Mar 4After lights, outlets and faucets + espresso machine delivered
Punch list and fixesTo do
Imogen · Fri, Mar 5 – Tue, Mar 9After equipment hooked up, tested
Health inspectionTo do
County · Mon, Mar 8After equipment hooked up, tested
Staff training and stockTo do
Tunde · Tue, Mar 9 – Thu, Mar 11
Soft opening for neighborsTo do
Everyone · Fri, Mar 12After punch list and fixes + health inspection + staff training and stock
Doors openTo do
Sat, Mar 13After soft opening for neighbors
This week and next
Fri, Feb 5Drywall finished and sanded. Kofi sweeps out so the floor can go down on a clean slab.
Mon, Feb 8 – Thu, Feb 11Rhys lays the floor. Nobody else on site while the adhesive cures.
Fri, Feb 12Painting starts, and Aylin finishes the counter in her workshop.
Needed from Handbell
By Mon, Feb 8Paint colors confirmed, so the paint is on site before Friday.
By Fri, Feb 12Sign artwork approved. The sign maker needs two weeks before it goes up on Mar 1.
By Mon, Mar 1Four baristas hired, ready to train from Tue, Mar 9.
DoneHealth inspection booked for Mon, Mar 8.
What sets the date
Drywall, flooring, paint, counter, lights and faucets, then equipment run back to back from Feb 1 to Mar 4. A day lost on any of them moves everything after it.
The plan has two spare days: Wed, Mar 10 and Thu, Mar 11, between the punch list and the soft opening. The counter has its own slack and can finish up to three working days late off site.
Changed since last week. Electrical rough-in finished on Wed, Jan 27, two days later than first planned, because the hood duct needed a new route. The inspection still passed on Fri, Jan 29, so nothing after it moved.
Who's who. Imogen Reyes, project manager · Kofi Mensah, site lead and carpentry · Marta Silva, plumbing · Dev Malhotra, electrical · Aylin Demir, millwork · Rhys Pugh, floors and paint · Tunde Adeyemi, owner of Handbell Coffee.